Nissan Terrano 2 from 1985 to 1999
1. Maintenance instruction and to maintenance
2. Car maintenance
3. Четырехцилиндровыв engines
4. VS engines
5. All engines
6. Systems of cooling, heating, ventilation and conditioning
7. Fuel and exhaust systems
7.1. Fuel system - general information
7.2. The fuel filter - replacement
7.3. Idling turns - check and adjustment
7.4. The fuel highway - repair
7.5. A cable of a drive of a butterfly valve - removal and installation
7.6. A pedal - removal and installation
7.7. The fuel pump - check
7.8. The fuel pump - removal and installation
7.9. System of electronic injection of fuel - general information
7.10. Units of control and measuring system with the processor ECCS block - general information
7.11. Decompression of fuel system
7.12. The butterfly valve case (for systems with preliminary injection of TBI of systems) removal and installation
7.13. Nozzle replacement
7.14. System of injection of fuel – adjustments System of preliminary injection (TBI)
7.15. Fuel system cleaning
7.16. Tank removal and installation
7.17. Fuel level sensor removal and installation
7.18. Tank washing
7.19. Exhaust system general information
7.20. Forward exhaust pipe removal and installation
7.21. Catalytic neytralizatorsnyaty and installation
7.22. Exhaust silencer removal and installation
7.23. Average pipe removal and installation
8. System of electric equipment of the engine
9. System of decrease in toxicity of exhaust gases
10. Mechanical transmission
11. Automatic transmissions
12. Coupling driveshaft and back bridge
13. A running gear of cars with a wheel formula 4x4
14. Brake system
15. Suspension brackets and steering
16. Body and furnish elements
17. Electric equipment system
 






7-14-sistema-vpryska-topliva-regulirovki-sistema-predvaritelnogo-vpryska-tbi.html

7.14. System of injection of fuel – adjustments System of preliminary injection (TBI)

Check and adjustment of the raised turns of idling
1. Warm up the engine.
2. Be convinced that the adjusting label of a cam is opposite to the center of the roller of draft of a cam. Otherwise adjust rotating the S1 screw. It is not possible if to adjust, replace a thermoelement (photo).
3. Check G gap between the roller of draft and a cam (photo). If necessary adjust a gap S2 screw rotation.
Proof-reader of idling of the conditioner (FICD system) check and adjustment
4. Warm up the engine.
5. Check idling turns.

14.3 Adjustment of the raised turns of idling on the case of a zaslonka 1. Thermoelement 2. Case of a heater 3. G 4 gap. Lever of a butterfly valve 5. Adjusting screw S2 6. Adjusting screw of a butterfly valve 7. Remove a cap 8. Draft ку


6. Turn on the conditioner and check idling turns.
7. If necessary adjust rotation of the screw (photo).
8. In default the valve of the proof-reader of idling execute the following checks (photo).
а). Disconnect 8штырьковый the socket.
14.7 Adjustment of turns of idling at turning on of the conditioner 1. Adjusting screw 2. Valve of the proof-reader of idling


б). Include ignition, transfer the conditioner switch to a working condition and check tension existence on conclusions of the socket (photo),
в). Check integrity of a winding of the valve.
Pneumoshock-absorber check and adjustment
10. Warm up the engine. Check idling turns, if necessary adjust.
11. Turn a zaslonka by hand so that the rod of the pneumoshock-absorber concerned the adjusting screw of a course of a rod and check turns of the engine (photo).
12. If necessary adjust turns rotation of the adjusting screw.

14.8 Check of the valve of the proof-reader on the V6 engine (And) and on the 4-cylinder engine (In) And 1,4. Valve of the proof-reader 2J3. At the included ignition and the conditioner 5. Check of a chain of a winding of the valve of B.Soyedineniye with weight 7. Checking of tension of B 1. Valve proof-reader


14.11 Pneumoshock-absorber 1 adjustment. Adjusting screw of the pneumoshock-absorber 2. Pneumoshock-absorber 3. Adjusting screw of a butterfly valve


14.13 Check of the valve of the raised turns of idling on the V6 engine (And) and on the 4-cylinder engine (In) And 1,3. Valve 2. Check of a chain of a winding of the valve B 1. Valve


14.17 The label of Q should be opposite to the center of a roller 1. Roller


14.18 Adjusting screw of a cam (And) and lock-nut


14.19а G Gap between a roller and a cam 1. Roller 2. Cam


Check of the valve of the raised turns of idling
13. Disconnect 8штырьковый the socket (photo) and check a chain of a winding of the valve.
14. If the gap is found, replace the valve. The new valve tighten & the set moment, having replaced laying
System of direct injection
System of the raised turns of idling check and adjustment (K24J engine)
15. Warm up the engine.
16. Stop the engine and remove the air filter.
17. Be convinced that the adjusting label (Q) is opposite to the roller center { a photo).
18. Adjust a cam, rotating the screw while the upper edge of a cam will not be established opposite to the center of a roller (photo).
19. Check G gap between a roller and a cam (photo). If necessary adjust a gap screw B rotation.

14.196 Adjustment of a butterfly valve 1. Roller 2. Draft 3. Screw B 4. This label is intended for other purpose (not for adjustment) 5. Cam



«previous page
7.13. Nozzle replacement
following page»
7.15. Fuel system cleaning